Greatworth to Southam (G2S) is the most North section of the C23 section of HS2 that is managed by EKFB JV. And meets the works that BBV are doing from Birmingham to Long Itchington.
Greatworth is split into three sections
North - Southam
Central - Chipping Warden
South - Greatworth
We will be looking for three specialist contractors to conduct the planting on G2S, one contractor per section. (total of 3 contractors)
Planting included Herbaceous, Shrub & Trees
Approx. volume Herbaceous 283,000, Shrub 1,000,000 and Trees 230,000 throughout the three sections as a whole.
There are gradients on the route, embankments and cuttings.
Supply of Trees, plants, stakes etc will be by the Employer (HS2) via the Contractor free issue to the Subcontractor.
Please express your interest within this package.